PR2F · Question #37

What is the name given to the individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks?

The correct answer is C. Risk Actionee. See the full explanation below for the reasoning.

Question

What is the name given to the individual assigned to carry out a risk response action or actions to respond to a particular risk or set of risks?

Options

  • ARisk Manage
  • BRisk Coordinator
  • CRisk Actionee
  • DRisk Owner

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    86% (18)