What name is given to the permissible deviation allowed above and below a plan's target for time and cost without escalating the deviation to the next level of management?

The correct answer is B. Tolerance. See the full explanation below for the reasoning.

Question

What name is given to the permissible deviation allowed above and below a plan's target for time and cost without escalating the deviation to the next level of management?

Options

  • AConcession
  • BTolerance
  • CProject Issue
  • DOff-specification

How the community answered

(46 responses)
  • A
    4% (2)
  • B
    74% (34)
  • C
    9% (4)
  • D
    13% (6)