Are the following statements regarding raising exceptions true or false? 1. If the stage is forecast to exceed its tolerances, the Project Manager should produce an Issue Report to capture and…
The correct answer is A. Only 1 is true. See the full explanation below for the reasoning.
Question
Are the following statements regarding raising exceptions true or false? 1. If the stage is forecast to exceed its tolerances, the Project Manager should produce an Issue Report to capture and analyze the details of the deviation 2. Where a Work Package is forecast to exceed its tolerances, the Project Manager may request the Team Manager to produce an Exception Plan
Options
- AOnly 1 is true
- BOnly 2 is true
- CBoth 1 and 2 are true
- DBoth 1 and 2 are false
How the community answered
(21 responses)- A86% (18)
- B10% (2)
- D5% (1)