EXIN
PR2F · Question #281
Which management level uses the mechanisms included within the Progress theme to control any unacceptable deviations?
The correct answer is C. All levels of management. See the full explanation below for the reasoning.
Question
Which management level uses the mechanisms included within the Progress theme to control any unacceptable deviations?
Options
- AOnly the Project Board
- BOnly the Project Manager
- CAll levels of management
- DOnly corporate or programme management
How the community answered
(22 responses)- A5% (1)
- B5% (1)
- C82% (18)
- D9% (2)
Community Discussion