Which of the following is mandatory in a PRINCE2 project?
The correct answer is B. Use of management stages. See the full explanation below for the reasoning.
Question
Which of the following is mandatory in a PRINCE2 project?
Options
- AUse of a separate person as Team Manager
- BUse of management stages
- CUse of Exception Plans
- DUse of Team Plans
How the community answered
(42 responses)- A10% (4)
- B83% (35)
- C2% (1)
- D5% (2)