PR2F · Question #277
Which of the following is a Project Board control?
The correct answer is B. Approve a Plan, with its relevant tolerances for the next management stage. See the full explanation below for the reasoning.
Question
Which of the following is a Project Board control?
Options
- AApproving a deviation of benefits tolerance
- BApprove a Plan, with its relevant tolerances for the next management stage
- CReview Checkpoint Reports to monitor progress
- DUse of project registers and logs to review progress
How the community answered
(36 responses)- A11% (4)
- B81% (29)
- C6% (2)
- D3% (1)