PR2F · Question #276

Which of the following is NOT within the authority of the Project Board?

The correct answer is D. Continuation where project-level tolerance is forecast to be exceeded. See the full explanation below for the reasoning.

Question

Which of the following is NOT within the authority of the Project Board?

Options

  • ATrigger premature closure of the project
  • BSetting stage-level tolerance
  • CAuthorizing initiation
  • DContinuation where project-level tolerance is forecast to be exceeded

How the community answered

(48 responses)
  • A
    13% (6)
  • B
    2% (1)
  • C
    6% (3)
  • D
    79% (38)