Which of the following is NOT within the authority of the Project Board?
The correct answer is D. Continuation where project-level tolerance is forecast to be exceeded. See the full explanation below for the reasoning.
Question
Which of the following is NOT within the authority of the Project Board?
Options
- ATrigger premature closure of the project
- BSetting stage-level tolerance
- CAuthorizing initiation
- DContinuation where project-level tolerance is forecast to be exceeded
How the community answered
(48 responses)- A13% (6)
- B2% (1)
- C6% (3)
- D79% (38)
Community Discussion