What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?
The correct answer is C. Time-driven. See the full explanation below for the reasoning.
Question
What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?
Options
- AEvent-driven
- BException based
- CTime-driven
- DAd-hoc
How the community answered
(44 responses)- A7% (3)
- B14% (6)
- C75% (33)
- D5% (2)