nerdexam
EXIN

PR2F · Question #275

What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?

The correct answer is C. Time-driven. See the full explanation below for the reasoning.

Question

What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?

Options

  • AEvent-driven
  • BException based
  • CTime-driven
  • DAd-hoc

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    14% (6)
  • C
    75% (33)
  • D
    5% (2)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice