PR2F · Question #274
The creation of an Exception Plan often follows which situation?
The correct answer is B. An Exception Report being submitted to the Project Board. See the full explanation below for the reasoning.
Question
The creation of an Exception Plan often follows which situation?
Options
- AA time or cost slippage occurs during a management stage
- BAn Exception Report being submitted to the Project Board
- CA Stage Plan is updated due to an urgent corrective action being taken
- DAn Issue Report being created
How the community answered
(23 responses)- A4% (1)
- B74% (17)
- C13% (3)
- D9% (2)