PR2F · Question #273

What factors need to be taken into consideration when identifying the number of management stages required? 1. Where key decisions points need to be 2. The amount of risk within the project 3. The…

The correct answer is B. 1,2,4. See the full explanation below for the reasoning.

Question

What factors need to be taken into consideration when identifying the number of management stages required? 1. Where key decisions points need to be 2. The amount of risk within the project 3. The number of technical stages 4. How confident the Project Board and Project Manager are with proceeding

Options

  • A1,2,3
  • B1,2,4
  • C1,3,4
  • D2,3,4

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    86% (30)
  • C
    3% (1)
  • D
    9% (3)