Which level of management has control over a Work Package, as long as they are within the Work Package tolerances?
The correct answer is C. Team Manager. See the full explanation below for the reasoning.
Question
Which level of management has control over a Work Package, as long as they are within the Work Package tolerances?
Options
- AProject Manager
- BProject Board
- CTeam Manager
- DCorporate or programme management
How the community answered
(23 responses)- A9% (2)
- B4% (1)
- C74% (17)
- D13% (3)