Which best describes a stakeholder?

The correct answer is C. Anyone that can affect, be affected by, or perceive to be affected by an initiative. See the full explanation below for the reasoning.

Question

Which best describes a stakeholder?

Options

  • AOnly those people internal to the project team
  • BAnyone that may affect the project
  • CAnyone that can affect, be affected by, or perceive to be affected by an initiative
  • DSomeone who has a financial interest/stake in an initiative