If people other than the Project Board members were doing Project Assurance, who would they report to?

The correct answer is B. The Project Board member overseeing the relevant area of interest. See the full explanation below for the reasoning.

Question

If people other than the Project Board members were doing Project Assurance, who would they report to?

Options

  • ACorporate or programme management
  • BThe Project Board member overseeing the relevant area of interest
  • CThe Project Manager
  • DThe Team Manager whose Work Package execution is being monitored

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    79% (19)
  • C
    4% (1)
  • D
    4% (1)