Which process ensures that plans for achieving the expected benefits are managed and reviewed?
The correct answer is C. Directing a Project. See the full explanation below for the reasoning.
Question
Which process ensures that plans for achieving the expected benefits are managed and reviewed?
Options
- AClosing a Project
- BInitiating a Project
- CDirecting a Project
- DStarting up a Project
How the community answered
(26 responses)- A8% (2)
- B4% (1)
- C73% (19)
- D15% (4)