Which process ensures that plans for achieving the expected benefits are managed and reviewed?

The correct answer is C. Directing a Project. See the full explanation below for the reasoning.

Question

Which process ensures that plans for achieving the expected benefits are managed and reviewed?

Options

  • AClosing a Project
  • BInitiating a Project
  • CDirecting a Project
  • DStarting up a Project

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    73% (19)
  • D
    15% (4)