Which of the following Plans can be approved by the Project Manager?
The correct answer is B. Team Plan. See the full explanation below for the reasoning.
Question
Which of the following Plans can be approved by the Project Manager?
Options
- AProject Plan
- BTeam Plan
- CException Plan at stage-level
- DStage Plan
How the community answered
(31 responses)- A3% (1)
- B81% (25)
- C6% (2)
- D10% (3)