PR2F · Question #132

Which of the following Plans can be approved by the Project Manager?

The correct answer is B. Team Plan. See the full explanation below for the reasoning.

Question

Which of the following Plans can be approved by the Project Manager?

Options

  • AProject Plan
  • BTeam Plan
  • CException Plan at stage-level
  • DStage Plan

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    81% (25)
  • C
    6% (2)
  • D
    10% (3)