Why does PRINCE2 recommend having three levels of plan?
The correct answer is D. To reflect the needs of the different levels of management involved in the project, stage and team. See the full explanation below for the reasoning.
Question
Why does PRINCE2 recommend having three levels of plan?
Options
- AThe more levels there are, the more stable the plan detail will become
- BAspects of planning become more difficult the further into the future they extend
- CTo reflect that there are 3 key stakeholder project interests
- DTo reflect the needs of the different levels of management involved in the project, stage and team
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- C6% (2)
- D81% (25)