Question

According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?

Options

  • AIt can be difficult to predict the actual performance of resources
  • BAll aspects of planning become more difficult the further into the future they extend
  • CSufficient detail is only known once the relevant stage has begun
  • DThe supplier is unlikely to comprehend the detailed schedule