According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?
The correct answer is B. All aspects of planning become more difficult the further into the future they extend. See the full explanation below for the reasoning.
Question
According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?
Options
- AIt can be difficult to predict the actual performance of resources
- BAll aspects of planning become more difficult the further into the future they extend
- CSufficient detail is only known once the relevant stage has begun
- DThe supplier is unlikely to comprehend the detailed schedule
How the community answered
(42 responses)- A12% (5)
- B81% (34)
- C2% (1)
- D5% (2)