PR2F · Question #133
In which process is it decided that an Exception Plan should be created to replace a Stage Plan?
The correct answer is A. Directing a Project. See the full explanation below for the reasoning.
Question
In which process is it decided that an Exception Plan should be created to replace a Stage Plan?
Options
- ADirecting a Project
- BControlling a Stage
- CManaging a Stage Boundary
- DClosing a Project
How the community answered
(42 responses)- A86% (36)
- B10% (4)
- C2% (1)
- D2% (1)