PMP · Question #999
Two project managers are working on separate projects that have identified the same subject matter expert (SME) as critical to their projects. Project A is using a predictive approach and Project B is
The correct answer is B. The project with the highest score in the program to improve the likelihood of success.. Two projects, one predictive and one agile, both require the same critical SME, necessitating a decision on resource allocation.
Question
Options
- AThe project with the less experienced project manager to improve the likelihood of success.
- BThe project with the highest score in the program to improve the likelihood of success.
- CProject A, because project planning was based on the assumption that the SME would be
- DProject B, because success in an agile project is determined by technical excellence.
How the community answered
(26 responses)- A8% (2)
- B69% (18)
- C19% (5)
- D4% (1)
Why each option
Two projects, one predictive and one agile, both require the same critical SME, necessitating a decision on resource allocation.
Allocating resources based on a project manager's experience level is not a primary criterion for maximizing overall project or program success when a critical resource is at stake.
When competing for a limited critical resource, the decision should be based on strategic alignment and overall program or organizational value. Allocating the SME to the project with the highest score in the program ensures the resource contributes to the initiative offering the greatest strategic benefit or return on investment, thereby maximizing the overall likelihood of success for the organization.
While predictive project planning might initially assume SME availability, a conflict arising necessitates prioritizing based on current strategic value rather than past assumptions, which might require adjusting the predictive plan.
Technical excellence is important in agile, but it is not the sole determinant of project success, nor does it automatically give an agile project priority over a predictive one for a shared critical resource; overall program value takes precedence.
Concept tested: Resource allocation prioritization
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
4B is the call. Resource allocation across competing projects comes down to portfolio or program prioritization, not delivery methodology or who planned first, so the highest-scored project wins the SME.
B is correct. Spin up a quick resource scenario in a sandbox and you will see the program score is the tiebreaker.
Agreed on B, but worth understanding why the tiebreaker works that way: program score reflects actual resource fit, so when everything else is equal, that is the logical place to look, not just a memorized rule.
B is the right call but the wording is weak. PMI wants you to think program-level prioritization, not who got there first. C is the trap because predictive planning feels like it locks in resources, but a fixed schedule does not override organizational priorities.