Question
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
Options
- AUse the retrospective meeting to better understand the root cause of the quality problems and put
- BHire an external company to add an additional layer of testing, making sure that the final product
- CCreate a reward system granting incentives to the team members who are able to catch more
- DSeek extra funding approval with the sponsor to replace junior team members for more
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Quality#Retrospective Meetings#Continuous Improvement#Root Cause Analysis