Question
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value. Which evaluation practice should the project lead use to obtain accurate usage data?
Options
- AEmbed a feedback form into the system for users to respond
- BBuild the functionality in the software to collect the operational usage data
- CSend out a questionnaire to all users regarding the most useful features
- DInterview a sampling of users to obtain the usage data
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Value delivery#Metrics and measurement#Benefits realization#Data collection