nerdexam
PMIPMI

PMP · Question #985

PMP Question #985: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #985. The question stem and answer options stay visible for context.

Submitted by yuriko_h· Apr 18, 2026Process

Question

A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met. Which three actions should the project manager do? (Choose three.)

Options

  • AIdentify in the iteration planning the acceptance criteria that meet quality standards.
  • BIdentify the acceptance criteria during the retrospective that meet the quality standards.
  • CAnalyze the lessons learned to determine appropriate testing metrics in quality standards.
  • DIncorporate performance metrics on the verified deliverables according to quality standards.
  • EPerform a risk analysis to determine the impact of not complying with quality standards.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Quality Management#Acceptance Criteria#Performance Metrics#Lessons Learned
Full PMP PracticeBrowse All PMP Questions