nerdexam
PMIPMI

PMP · Question #950

PMP Question #950: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #950. The question stem and answer options stay visible for context.

Submitted by kev92· Apr 18, 2026Process

Question

A project manager is initiating a project to create a new service that has never been done before in their organization. The project manager is trying to determine what resources are required for their project team but is receiving conflicting resource requirements from the team, sponsor, and key stakeholders. What should the project manager do next?

Options

  • AIdentify the resources that are agreed upon to initiate the project and request additional resources
  • BDetermine if there is a subject matter expert (SME) who has expertise in the new service to assist
  • CEvaluate and prioritize the resource requests from the project's key stakeholders.
  • DEvaluate the resource options and propose alternatives to the project team for their approval.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Planning#Expert Judgment#Stakeholder Engagement#Knowledge Gaps
Full PMP PracticeBrowse All PMP Questions