nerdexam
PMIPMI

PMP · Question #949

PMP Question #949: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #949. The question stem and answer options stay visible for context.

Submitted by paula_co· Apr 18, 2026People

Question

A project lead is managing a construction project in an isolated location. There have been delays due to difficult working conditions, which include team sickness and absences. How should the project lead manage those issues to get the project back on track?

Options

  • AAsk for additional budget because the project end will be delayed.
  • BIdentify the causes of the issues in order to find a suitable solution.
  • CReview the project scope in order to simplify it and shorten project duration.
  • DAsk human resources (HR) to find individuals to replace team members.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Problem Solving#Root Cause Analysis#Team Management#Issue Management
Full PMP PracticeBrowse All PMP Questions