nerdexam
PMIPMI

PMP · Question #947

PMP Question #947: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #947. The question stem and answer options stay visible for context.

Submitted by olafpl· Apr 18, 2026Process

Question

A project manager is leading a team that is new to agile. During the kickoff meeting, one team member asks how risks will be managed using agile approaches. How should the project manager respond?

Options

  • ARisk management is a collaborative effort and will be managed during each iteration.
  • BRisks are managed by the project manager and forecasted at the beginning of each project.
  • CRisks will be managed during a retrospective session with all of the team members.
  • DRisks are managed by the team and they will be analyzed during risk management kickoff.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Risk Management#Iterative Management#Team Collaboration#Agile Principles
Full PMP PracticeBrowse All PMP Questions