Question
A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level. How should the project manager ensure that project risks are reported accurately in the risk register?
Options
- AUpdate the risks in the risk management plan
- BReview the risks throughout project execution
- CList the project risks identified in the kick-off meeting
- DPlan to update the risks at project closure