Question
A project manager recently finished a project and started managing a new project with a different supervisor. As part of the early project activities, the supervisor from the original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor. What should the project manager do to resolve this conflict?
Options
- AEnsure the new supervisor takes the lead when being challenged
- BGive the project team time to work through the issues with the new supervisor
- CImmediately remove the resource from the project team
- DCommunicate with the resource on the roles and responsibilities of this project