nerdexam
PMIPMI

PMP · Question #930

PMP Question #930: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #930. The question stem and answer options stay visible for context.

Submitted by mike_84· Apr 18, 2026Process

Question

A project manager is executing a large project with many stakeholders. One of the primary stakeholders is requesting a change to the project scope. The project manager knows that this scope change will not require much effort from the project team. The project manager is worried that going through the full change control process will hold up the project schedule. What should the project manager do?

Options

  • AAsk the primary stakeholder for their official approval to avoid the change control process.
  • BImplement the change in order to avoid changes to the schedule baseline.
  • CReject the change request because the project is already being executed.
  • DSubmit a formal change request since the change is affecting the project baseline.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Integrated Change Control#Scope Baseline#Process Adherence
Full PMP PracticeBrowse All PMP Questions