nerdexam
PMIPMI

PMP · Question #887

PMP Question #887: Real Exam Question with Answer & Explanation

The correct answer is D: Document the new risks in the project benefits management plan and risk management plan.. When a major external crisis threatens project outcomes, the project manager should immediately identify and document these new risks in the project's risk and benefits management plans.

Submitted by suresh_in· Apr 18, 2026Process

Question

A project manager is leading a project when a major crisis suddenly causes an economic downturn, which may threaten the project outcome. What should the project manager do?

Options

  • AUpdate the project charter and benefits management plan with the current realities.
  • BCreate a proposal suggesting that the project sponsor terminate the project.
  • CReallocate some project resources to other assignments in the organization.
  • DDocument the new risks in the project benefits management plan and risk management plan.

Explanation

When a major external crisis threatens project outcomes, the project manager should immediately identify and document these new risks in the project's risk and benefits management plans.

Common mistakes.

  • A. Updating the project charter is typically reserved for fundamental changes to project authorization or high-level objectives, which is usually a consequence of a major crisis, not the initial risk identification step.
  • B. Proposing project termination as the first response is premature; a thorough risk assessment and impact analysis should precede such an extreme recommendation.
  • C. Reallocating resources without first understanding the full impact of the crisis and reassessing project needs or viability is a reactive measure that could further jeopardize the project.

Concept tested. Risk identification and management

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/seventh-edition

Topics

#Risk Management#External Risks#Benefits Realization#Risk Identification

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions