PMIPMI
PMP · Question #868
PMP Question #868: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #868. The question stem and answer options stay visible for context.
Submitted by fatema_kw· Apr 18, 2026Process
Question
One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager. What should the project manager do?
Options
- AReview the integrated change control process with all the stakeholders.
- BEscalate the misalignment to the project management office (PMO) and the functional manager's
- CAsk the project management office (PMO) to recover the cost of fixing it from the other team's
- DRequest dedicated business resources to support functional testing.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Integrated Change Control#User Acceptance Testing (UAT)#Scope Management#Process Adherence