PMP · Question #841
PMP Question #841: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #841. The question stem and answer options stay visible for context.
Question
During the execution phase, the project manager discovered that the deliverables are not meeting the quality specifications requested by the main stakeholder. This has caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost performance index (CPI) from 1.5 to 1.1. What action should the project manager take to mitigate the issue of the deliverables being rejected during the next iteration?
Options
- ASubmit a change request to prioritize resolutions for the quality issue to minimize the impact on
- BReinforce the definition of done (DoD) during sprint planning so that the team has a common
- CCreate a dedicated sprint to complete all of the pending specifications from previous sprints.
- DAssure that the product backlog is properly prioritized to avoid dependencies that cause rejection.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.