PMP · Question #842

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the lat

The correct answer is B. Make sure all stakeholders have access to the system and know where to find project artifacts.. Stakeholders are unable to locate the project schedule despite a repository being available, indicating a communication management issue where access or knowledge of the system is lacking. The project manager should ensure proper access and guidance for stakeholders to find proje

Submitted by katya_ua· Apr 18, 2026People

Question

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule. What should the project manager do?

Options

  • AAdvise the project management office (PMO) that there is a resource gap for sharing project
  • BMake sure all stakeholders have access to the system and know where to find project artifacts.
  • CEscalate the issue to the steering committee and ask them to deal with the stakeholders' lack of
  • DSend the project schedule via email to the stakeholders who need that information.

How the community answered

(52 responses)
  • A
    12% (6)
  • B
    81% (42)
  • C
    6% (3)
  • D
    2% (1)

Why each option

Stakeholders are unable to locate the project schedule despite a repository being available, indicating a communication management issue where access or knowledge of the system is lacking. The project manager should ensure proper access and guidance for stakeholders to find project artifacts in the designated system.

AAdvise the project management office (PMO) that there is a resource gap for sharing project

Advising the PMO of a resource gap is an overreaction; the issue is likely a communication or access problem, not a lack of resources for sharing.

BMake sure all stakeholders have access to the system and know where to find project artifacts.Correct

This action directly addresses the root cause of the problem by ensuring stakeholders have both the necessary access to the artifact repository and the knowledge of how to navigate it to find information like the project schedule. It promotes self-service and consistent information access.

CEscalate the issue to the steering committee and ask them to deal with the stakeholders' lack of

Escalating to the steering committee is an inappropriate first step for a common communication and access issue that the project manager should resolve directly.

DSend the project schedule via email to the stakeholders who need that information.

Sending the schedule via email is a short-term workaround that doesn't solve the underlying problem of stakeholders being unable to use the designated repository for all project artifacts.

Concept tested: Communication management and information distribution

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Stakeholder Communication#Information Management#Project Artifacts#Access Management

Community Discussion

5
Hiroshi T.Hiroshi T.Jun 26, 2026

B is correct, confirmed on exam last week. The PMBOK Guide Sixth Edition, Section 10.2.2.4, is explicit that project information flow depends on both system access and stakeholder awareness of where artifacts live. A and C escalate a minor access problem that the project manager owns outright, and D creates a secondary schedule copy outside the repository, which defeats the configuration management purpose. The right move is to fix the access gap and point stakeholders to the authoritative source.

14
Luis F.Luis F.Jun 3, 2026

B is right. PM owns artifact access and has to show folks where things live.

5
Toby R.Toby R.Jun 30, 2026

Confirmed B on my exam last month. The key is that the software already exists, so the PM just needs to make sure stakeholders have access and know where to look rather than creating a workaround like D.

4
Wei W.Wei W.Jun 18, 2026

D is a quick fix but kills transparency. B keeps the artifacts where everyone can self-serve.

3
Nina C.Nina C.Jun 10, 2026

Agreed on B. As a teacher I learned you have to show people where things are, not just put them somewhere.

1