nerdexam
PMIPMI

PMP · Question #84

PMP Question #84: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #84. The question stem and answer options stay visible for context.

Submitted by brentm· Apr 18, 2026Process

Question

A project manager is assigned to a project where a vendor has been engaged to build a new system. One week before user acceptance testing (UAT) is scheduled, the vendor informs the project manager that they can only deliver half of the promised functions by the UAT start date. What should the project manager do next?

Options

  • ACommunicate with the vendor and project team and explore possibilities for resolving the issue
  • BWait until the vendor cannot deliver and then invoke liquidated damages based on the contract
  • CEscalate to management and prepare for project closure by canceling the contract with this
  • DAdjust the project schedule to accommodate the current development progress of the vendor

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Issue Management#Stakeholder Communication#Procurement Management#Problem Solving
Full PMP PracticeBrowse All PMP Questions