PMP · Question #85
PMP Question #85: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #85. The question stem and answer options stay visible for context.
Question
In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician. The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technician's poor performance as the reason for the conflict. How should the project manager resolve the problem?
Options
- AUse a direct, collaborative approach with the technician and supervisor
- BProvide a just-in-time training to the technician to improve their skill set
- CReplace the technician with a high performing resource as time is critical
- DTalk to the supervisor to tone down their approach and attitude
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.