nerdexam
PMIPMI

PMP · Question #818

PMP Question #818: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #818. The question stem and answer options stay visible for context.

Submitted by fatema_kw· Apr 18, 2026Process

Question

A project manager is assigned to a project. The project schedule and costs are tight, and the project manager determined that there is a lack of resources to deliver this project. What should the project manager do?

Options

  • AIdentify the resource requirements and communicate them to the stakeholders seeking resources.
  • BUpdate the risk register noting that, due to the lack of available resources, the project is likely to
  • CDefine the work breakdown structure (WBS), identify the resource gaps, and reduce project
  • DFormalize a scope change request with the stakeholders to adjust the project scope with the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Scope Management#Change Management#Constraint Management
Full PMP PracticeBrowse All PMP Questions