PMP · Question #817

A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices th

The correct answer is B. Reevaluate the probability of the risk occurrence and mitigation strategy.. When a risk mitigation strategy fails, the project manager should reevaluate both the risk's probability and the effectiveness of the current mitigation strategy to formulate a more appropriate response.

Submitted by thandi_sa· Apr 18, 2026Process

Question

A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results. How should the project manager proceed?

Options

  • AReview the procurement performance to identify the root cause
  • BReevaluate the probability of the risk occurrence and mitigation strategy.
  • CIssue a change request to apply the risk response plan for this risk.
  • DAudit the procurement process to identify why the mitigation did not work.

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    80% (24)
  • C
    3% (1)
  • D
    13% (4)

Why each option

When a risk mitigation strategy fails, the project manager should reevaluate both the risk's probability and the effectiveness of the current mitigation strategy to formulate a more appropriate response.

AReview the procurement performance to identify the root cause

Reviewing procurement performance might be a part of identifying the root cause later, but the immediate problem is the failed risk mitigation, which needs a direct re-evaluation of the risk and its response.

BReevaluate the probability of the risk occurrence and mitigation strategy.Correct

If a mitigation strategy didn't produce expected results, it indicates that either the understanding of the risk's likelihood was inaccurate, or the chosen mitigation itself was ineffective or poorly implemented. Reevaluating both the probability of the risk and the strategy allows for a course correction to develop a more robust and effective response.

CIssue a change request to apply the risk response plan for this risk.

Issuing a change request to apply the risk response plan isn't the right next step; the problem is that the existing plan's mitigation failed, so a new or revised plan is needed, which might then lead to a change request if scope or budget is affected.

DAudit the procurement process to identify why the mitigation did not work.

Auditing the procurement process is a more extensive and later step, typically for systemic issues or after broader project completion; the immediate need is to address the specific failed risk mitigation.

Concept tested: Risk monitoring and control

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Risk Monitoring#Risk Response Planning

Community Discussion

5
Orla P.Orla P.Oct 26, 2025

Confirmed B on exam last week. When a mitigation strategy does not produce the expected results, the PM reevaluates the probability and impact of the risk and updates the mitigation approach. C sounds plausible but a change request is premature until you have a revised response plan. A and D skip straight to procurement audits without first reanalyzing the risk itself, which is the immediate next step in Monitor Risks.

14
Yuki V.Yuki V.Oct 29, 2025

Agreed on B, and the key word I watched for was reevaluate, since Monitor Risks is about checking whether your responses actually worked before you escalate or change anything.

0
Yuki V.Yuki V.Nov 10, 2025

B on my exam last week. Does reevaluating mean we update the register too or just the strategy?

4
Orla P.Orla P.Nov 12, 2025

B is right, and yes, reevaluating means you revisit the actual register entries too, not just the strategy document, since risks and their scores can shift between reviews.

0
Lena V.Lena V.Nov 3, 2025

Saw this last month, mitigation failed means reassess, not jump to changes.