nerdexam
PMIPMI

PMP · Question #817

PMP Question #817: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #817. The question stem and answer options stay visible for context.

Submitted by thandi_sa· Apr 18, 2026Process

Question

A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results. How should the project manager proceed?

Options

  • AReview the procurement performance to identify the root cause
  • BReevaluate the probability of the risk occurrence and mitigation strategy.
  • CIssue a change request to apply the risk response plan for this risk.
  • DAudit the procurement process to identify why the mitigation did not work.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Monitoring#Risk Response Planning
Full PMP PracticeBrowse All PMP Questions