Question

A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?

Options

  • AA detailed mitigation plan on the risks for each work method and the tools used
  • BA technology roadmap for creating similar deliverables in the future with the same tools
  • CAn agreed-upon work method and tools that should fit the business need and project constraints
  • DA consensus that everything will run as anticipated once the tools and work methods are

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Work Methods#Tools Selection#Project Planning#Deliverable Development
Full PMP PracticeBrowse All PMP Questions