nerdexam
PMIPMI

PMP · Question #812

PMP Question #812: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #812. The question stem and answer options stay visible for context.

Submitted by emma.c· Apr 18, 2026People

Question

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder in order to provide necessary resources. However, the stakeholder is refusing to get involved because the stakeholder thinks that there is no benefit in using the project deliverable. What should the project manager do to resolve this?

Options

  • AConsider the stakeholder as a risk and evaluate possible solutions with the project team.
  • BEscalate to the project sponsor due to the political nature of the issue.
  • CImprove communication with the stakeholder to obtain their assistance in the future.
  • DMeet with the stakeholder to discuss the impact of the deliverable.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Engagement#Communication#Influencing Stakeholders#Project Charter
Full PMP PracticeBrowse All PMP Questions