PMIPMI
PMP · Question #804
PMP Question #804: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #804. The question stem and answer options stay visible for context.
Submitted by alyssa_d· Apr 18, 2026Process
Question
A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024. What does this value mean for the project?
Options
- AThe project is earning less value than was planned
- BThe project has started exceeding the planned cost
- CThe project has earned more value than planned
- DThe project is close to exceeding the planned cost
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Earned Value Management#Cost Performance Index#Project Cost Management#Performance Monitoring