Question

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Options

  • AAsk the product owner if some low-priority stories could be cut from the sprint
  • BContinue with the sprint as the progress shows buffers for potential interruptions
  • CAsk the project team to select any additional stories as they have additional capacity than
  • DContinue with the sprint work as planned and keep monitoring

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Scrum#Burndown Chart#Sprint Management#Monitoring Progress