nerdexam
PMIPMI

PMP · Question #736

PMP Question #736: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #736. The question stem and answer options stay visible for context.

Submitted by yuriko_h· Apr 18, 2026Process

Question

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?

Options

  • AConfirm to the stakeholder that the risk register has been completed and validated by all
  • BPerform a risk analysis directly with the stakeholder who raised the risk and update the risk
  • CCommunicate the risk to the steering committee and request a mitigation plan from senior
  • DAdd the risk to the risk register and reevaluate the register with help from the project team and

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Identification#Risk Register#Project Team Collaboration
Full PMP PracticeBrowse All PMP Questions