Question
A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages. What should the project manager do?
Options
- AConfirm to the stakeholder that the risk register has been completed and validated by all
- BPerform a risk analysis directly with the stakeholder who raised the risk and update the risk
- CCommunicate the risk to the steering committee and request a mitigation plan from senior
- DAdd the risk to the risk register and reevaluate the register with help from the project team and
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Risk Identification#Risk Register#Project Team Collaboration