nerdexam
PMIPMI

PMP · Question #713

PMP Question #713: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #713. The question stem and answer options stay visible for context.

Submitted by fernanda_arg· Apr 18, 2026Process

Question

Five agile teams working together on a product recently performed release planning. Midway through the project, each team showed that their progress was on track. When all of the teams integrated at the product level, many integration issues were observed. The overall product release progress declined with predictions showing the committed content will not be able to be accomplished. What should the project manager have done differently?

Options

  • APerformed a Scrum of Scrums on a regular basis to help the teams remove impediments
  • BFormed a separate quality assurance team to test all items coming from each team at the end of
  • CArranged an online session on the integration concept and suggested tools to the teams
  • DEnsured frequent and continuous integration of work to obtain early feedback and continuous

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Integration#Continuous Integration#Multi-team Agile#Feedback Loops
Full PMP PracticeBrowse All PMP Questions