PMIPMI
PMP · Question #714
PMP Question #714: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #714. The question stem and answer options stay visible for context.
Submitted by paula_co· Apr 18, 2026People
Question
A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented. What should the project manager do?
Options
- AAsk the team member to learn the new system as on-the-job training.
- BIssue a change request to extend the project schedule.
- CEscalate the team member's performance to the project sponsor.
- DAssign an experienced resource to support the team member.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Team Development#Skill Gap Management#Resource Allocation#Problem Solving