nerdexam
PMIPMI

PMP · Question #709

PMP Question #709: Real Exam Question with Answer & Explanation

The correct answer is C: A hybrid approach will allow for management of the requirement uncertainties as well as the date. Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.

Submitted by saadiq_pk· Apr 18, 2026Process

Question

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?

Options

  • AA hybrid approach will enable project activities to start immediately and allow for a plan for the
  • BA hybrid approach will allow the project manager to revise the product specifications
  • CA hybrid approach will allow for management of the requirement uncertainties as well as the date
  • DA hybrid approach will ensure the delivery date is accomplished and will eliminate product

Explanation

Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.

Topics

#Hybrid Project Management#Adaptive Approaches#Predictive Approaches#Requirement Management

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions