PMP · Question #709
PMP Question #709: Real Exam Question with Answer & Explanation
The correct answer is C: A hybrid approach will allow for management of the requirement uncertainties as well as the date. Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.
Question
A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?
Options
- AA hybrid approach will enable project activities to start immediately and allow for a plan for the
- BA hybrid approach will allow the project manager to revise the product specifications
- CA hybrid approach will allow for management of the requirement uncertainties as well as the date
- DA hybrid approach will ensure the delivery date is accomplished and will eliminate product
Explanation
Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.