nerdexam
PMI

PMP · Question #709

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The

The correct answer is C. A hybrid approach will allow for management of the requirement uncertainties as well as the date. Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.

Submitted by saadiq_pk· Apr 18, 2026Process

Question

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the project manager has decided to use a hybrid approach. Why did the project manager choose a hybrid approach?

Options

  • AA hybrid approach will enable project activities to start immediately and allow for a plan for the
  • BA hybrid approach will allow the project manager to revise the product specifications
  • CA hybrid approach will allow for management of the requirement uncertainties as well as the date
  • DA hybrid approach will ensure the delivery date is accomplished and will eliminate product

How the community answered

(33 responses)
  • A
    12% (4)
  • B
    3% (1)
  • C
    82% (27)
  • D
    3% (1)

Explanation

Without knowing what is the requirement, as a project manager you cannot plan or schedule. Scope of a project comes from requirements. Schedule development can only be done scope is defined and validated - because it is Hybrid.

Topics

#Hybrid Project Management#Adaptive Approaches#Predictive Approaches#Requirement Management

Community Discussion

6
Mei-Ling H.Mei-Ling H.Jul 5, 2026

C is correct. The stem has two constraints: unclear requirements and a fixed regulatory date. Hybrid lets you handle the uncertainty with iterative work on the requirements while still using predictive planning for the compliance deadline. D is a trap because "ensure" and "eliminate" are absolutes that no methodology can guarantee. A is also tempting but the text is cut off and does not address the uncertainty side, which is the whole point of choosing hybrid over pure predictive.

18
Yusuf A.Yusuf A.Jul 7, 2026

The D trap is exactly what a senior PM warned me about, those absolute words like ensure and eliminate almost never survive in real projects, but I would add that the fixed regulatory date is the real driver here since you could also handle unclear requirements in pure agile if there were no compliance deadline.

0
Hiroshi T.Hiroshi T.Jun 26, 2026

C is the only option that addresses both constraints in the stem: unclear requirements and a fixed regulatory date. D is the trap because hybrid does not eliminate product uncertainty, it manages it alongside the committed delivery date. PMI.org, PMBOK Guide 7th edition, section on development approaches and life cycles, confirms hybrid combines predictive and adaptive to balance fixed constraints with evolving scope.

5
Mei-Ling H.Mei-Ling H.Jun 27, 2026

Agreed on C, but watch the qualifier if the stem says most uncertainty instead of just uncertainty, because that pushes toward adaptive-dominant hybrid and the answer edge gets thinner.

0
Yusuf A.Yusuf A.Jul 5, 2026

Saw this on my exam last month, my lead always says hybrid handles both uncertainty and fixed dates, so C.

3
Mei-Ling H.Mei-Ling H.Jul 7, 2026

C is correct but be careful with the word always, because hybrid specifically means the predictive side handles the fixed dates while the adaptive side handles uncertainty, not that a single hybrid approach automatically gives you both.

0
Full PMP Practice