PMP · Question #677
PMP Question #677: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #677. The question stem and answer options stay visible for context.
Question
A customized module is being implemented into an off-the-shelf enterprise resource planning (ERP) solution. The project scope has been clearly defined by the sponsor, and the project manager is close to starting user acceptance testing. However, the newly elected government introduced a significant package of taxation reforms. What should the project manager do?
Options
- AContact the finance team and ask for advice.
- BPut the project on hold and wait for information.
- CAssess the potential impact with the project team.
- DContinue with user testing as planned.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.