PMIPMI
PMP · Question #654
PMP Question #654: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #654. The question stem and answer options stay visible for context.
Submitted by anjalisingh· Apr 18, 2026Process
Question
A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project. What should the project manager do next?
Options
- AEscalate the issue of the additional requirements to the executive leadership team.
- BAdjust the scope baseline and schedule baseline accordingly.
- CImplement all the requirements the customer has requested.
- DRefer the stakeholder to the delivery specifications in the statement of work (SOW).
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Scope Management#Stakeholder Management#Contract Management#Change Control