PMIPMI
PMP · Question #634
PMP Question #634: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #634. The question stem and answer options stay visible for context.
Submitted by anna_se· Apr 18, 2026Process
Question
A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule. What should the project manager do next?
Options
- AUpdate the sponsor of the potential issue and ask for any suggestions.
- BValidate the information and update the risk management plan.
- CSource second-hand equipment in order to prepare for any delivery delays.
- DUpdate the risk register and discuss it with the project stakeholders.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Procurement Management#Information Validation#Schedule Management