Question
A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details. What two things should the project manager do? (Choose two.)
Options
- ADiscuss the issue with the external supplier's authority.
- BGather additional information and estimate the impact.
- CWait for the client to raise a concern and collect more information.
- DReview the lessons learned from similar past projects.
- EUpdate the risk log and bring this up in the meeting with the client.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management Process#Proactive Issue Management#Stakeholder Communication#Risk Log Updates