PMP · Question #587

PMP Question #587: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #587. The question stem and answer options stay visible for context.

Submitted by obi.ng· Apr 18, 2026Process

Question

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope. What should the project manager do first?

Options

  • ADiscuss the requested change with the sponsor.
  • BEvaluate the cost of the additional requested work.
  • CDiscuss the requested change with the team.
  • DEvaluate the impact and submit a change request.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Scope Management#Team Collaboration