PMIPMI
PMP · Question #578
PMP Question #578: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #578. The question stem and answer options stay visible for context.
Submitted by certguy· Apr 18, 2026Process
Question
A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages. What is the project manager doing?
Options
- AResource leveling
- BWork breakdown structure (WBS)
- CDecomposition
- DNetwork diagram
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Decomposition#Work Breakdown Structure (WBS)#Scope Management#Project Planning